Where Do You Keep the Spare Part That Gets a Water Pump Running Again?

Ark Humanitarian Group’s first water strategy plans for repairs and spare parts before new construction. Here is why, and what it can’t decide without local partners.

By , co-founder and board member, Ark Humanitarian GroupNovember 24, 20265 min readRead original PDF (4 pages)

A broken handpump is rarely a mystery. Often the part that would fix it is small and cheap. UNICEF’s supply catalog lists a standard kit of fast-moving spares for one common pump model at an indicative $8.70. The hard question is where that kit sits on the day the pump fails, and who can get it to the well.

The gap is large. Handpumps serve more than 184 million people in rural sub-Saharan Africa, and at least 100,000 of an estimated 500,000 to 1.3 million are not working, according to researchers writing in The Conversation Africa in March 2026. Twenty years earlier, a World Bank and RWSN review of 25 studies from 15 countries found that about 30% of potentially working handpumps in Africa were out of service at any given time. Pumps fell out of use, it said, often because spare parts were unavailable.

Two decades apart, the two studies describe the same problem. That tells me the hard part was never drilling the well.

Repair comes first

Ark Humanitarian Group’s ten-year water strategy for Africa, Project 000, makes a deliberate choice about order. It puts repairing existing systems first, then protecting water sources, then adding modular supply, ahead of large new infrastructure. It names local supply chains for maintenance and critical spares as a focus.

The plan also tries to pay for the unglamorous years. It sets aside a renewal reserve equal to 1% of direct capital each year. It requires operators to be licensed and would pay them for delivery that has been verified. It releases money in tranches at decision gates, each tied to evidence, with an independent engineer signing off at set points. And it measures success in households served, verified hours of service and water quality, not in the number of things built.

This is a plan on paper. The strategy is a pre-feasibility report. It has no funding commitment, no partners and no confirmed sites, and the countries and example settings it names are illustrations, not choices. Our transparency page says the same about every project we publish.

I came to this work from business, where I learned that a signed contract is a promise someone else has to keep. A pump without a parts chain is a promise no one can keep, and it is made to a whole village.

What twenty years of evidence say about parts

The 2006 review is blunt about why parts chains fail. A private shop stocks what sells. The review estimated that a distributor might need around 200 pumps within 20 kilometers of an outlet to make stocking parts pay, a density rarely found where people are spread thin. In those places, it suggested, a publicly supported chain fits better, and most African countries might need 10 to 20 years of subsidized supply.

It also names what the successful chains had in common: someone managing the chain for the long term, with a plan for how outside support ends; simpler technology; enough demand; a small number of standard pump models; and parts sold alongside installation and repair services, with government backing. Ghana, it noted, allowed only four pump types in new installations, which concentrates demand for each part.

And it records what went wrong. In Malawi, a parts network that had been privatized failed. In Ghana, the central distributor still depended on donor support.

What newer data adds

The 2026 study looked at maintenance rather than parts. Its authors analyzed about 47,000 records covering 3,584 pumps over a decade, under three different approaches. In Malawi, the organization called communities to check on their pumps. In Ethiopia, communities were expected to call in when a pump broke, and many breakdowns went unreported. In the Central African Republic, mechanics visited on a fixed schedule.

Their finding is the kind a planner can use. Regular scheduled maintenance cost no more than doing none, and in some settings it cut downtime by up to 60%. They also found waste in the other direction, with some pumps serviced three times a year when twice would have done. Their advice to funders was to treat maintenance as part of water access, to support local supply of affordable parts and to train people to do repairs.

Where should the spare part be?

Reading that evidence together, I see three places a part can sit, and each comes with a condition.

Where the part sitsWhere it fitsWhat it needs
A private shopMany pumps of the same few models close togetherEnough sales to earn the shelf space
A public or district storeAreas where pumps are too scattered for a shop to profitA budget, a manager and a plan for restocking
The mechanic’s own kitRepairs sold together with the part, on a schedule or on callWorking capital, and a way to restock after each repair

A plan written far away can’t honestly choose among them. The right answer depends on how many pumps are nearby, which models they are, what the roads do in the rainy season and who people already trust to fix things. Those are local facts. The most a strategy can do is leave room for them, and refuse to release money until they’re known.

What local partners would still need to decide

  1. Which existing water points to fix first, based on a survey with the local water authority.
  2. Which pump models and part standards apply under national policy.
  3. Where spares are stocked (district stores, private retailers or mechanics’ kits) and who owns the inventory.
  4. Who repairs, and how area mechanics are trained, certified and paid.
  5. How breakdowns get reported: whether mechanics visit on a schedule, communities call in, or someone calls them.
  6. Who pays, through tariffs or subsidies, and how the renewal reserve is held and released.
  7. Which roads, ports and seasons limit delivery, and what stock buffers that requires.
  8. What gets monitored, and who is obliged to act on the data.

Tell us where the plan is wrong

If you have run a spares chain or a repair network, you know things this strategy doesn’t. Tell us which of its assumptions would fail in your district, and why. The partner page is the place to start.

Project 000 is the work of Ark Humanitarian Group’s team.

Sources: Project 000 and Ark Humanitarian Group’s transparency page; Oyo, Spare Part Supplies for Handpumps in Africa (WSP–Africa and RWSN, 2006); Zhai, Pedraza Martinez, Mejia, Bretthauer and Parker in The Conversation Africa (March 29, 2026, via AllAfrica); UNICEF supply catalog, item S0009194 (indicative price).